At the former Sonoma Developmental Center, California State Parks sends visitors to public parking along Harney Road and in through the eastern metal gate onto Sunrise Road. Its guided outings around Lake Suttonfield start at Harney and Railroad and follow an unpaved route of roughly 2.5 miles. On the east side, the paved Sunrise/Baker loop is a flat walk of 45 to 50 minutes. It passes the old farm, the horse corral, the dairy and a seasonal wetland.
The land between these trails and Arnold Drive is less settled. On the 180-acre core campus, a developer has proposed 990 homes, a 150-room hotel and about 130,000 square feet of commercial space. The county's environmental review of that plan will not be published until spring 2027. A buyer comparing Glen Ellen with the rest of Sonoma Valley this winter is weighing two different timelines at Eldridge. The open space is already set. The housing is a plan whose construction schedule runs to 2036, and the environmental review it waits on has already been pushed back.
State Parks runs the SDC open space. On Oct. 14, 2026, the agency said it had filed paperwork in September to amend the General Plan for Jack London State Historic Park so that it takes in the 765-acre SDC tract, and that State Parks would keep operating it. The agency describes the acreage as the link between Jack London State Historic Park and Sonoma Valley Regional Park, with connecting trails between them.
The land is managed as a working landscape. In late October, State Parks announced a planned burn of up to 29 acres east of Lake Suttonfield and said nearby trails could close while it burned. For anyone who regularly hikes up from Harney Road, that kind of closure is a routine part of how the park runs.
About 58 more acres went to CAL FIRE in February 2024 for its proposed Lake Napa Unit headquarters. So a Glen Ellen buyer can already count on public land under state agencies along much of the property's edge. None of it depends on what happens to the core campus. Glen Ellen's link to Jack London, which we followed through the author's 150th anniversary season, now includes a much larger park next door.
The core campus plan comes from Eldridge Renewal LLC, a partnership of Rogal & Partners and The Grupe Company. The state Department of General Services chose the team in February 2025. When the Sonoma Index-Tribune reported at the end of August 2026, the department still owned the campus.
The application calls for 990 homes. Of these, 200 would be deed-restricted for lower-income households, and five homesites would be set aside for people with intellectual or developmental disabilities. The plan also includes about 67 acres of parks, recreation and open space, along with trails, community facilities and a site for a new fire station and evacuation command center.
The applicant's phasing schedule appears in the county's August 2025 Notice of Preparation. It is the clearest view of how long the campus could be under construction:
| Phase | Homes | Other elements | Applicant's projected dates |
|---|---|---|---|
| 1 | 241 | 150-room hotel, conference center, reuse of the historic Main Building, Central Green | Site work March 2027, finished August 2032 |
| 2 | 469 | Agrihood east of Sonoma Creek, 100 affordable senior apartments, Firehouse Park | Site work August 2030, finished February 2035 |
| 3 | 280 | Environmental center on Orchard Road, Redwood Park, Confluence Park | Site work February 2033, finished August 2036 |
The phases overlap. Under the plan as filed, site work would be going on somewhere on the campus for about nine and a half years. Phase 1 lists possible uses for the restored Main Building, including a food hall, a screening room, co-working space and an event hall. Those would be the first parts of the project a Glen Ellen household could use. Under this schedule, they would arrive after five years of construction at the earliest.
The applicant's March 2027 start for Phase 1 was drawn up before the environmental impact report was delayed. At the Aug. 3 meeting in Glen Ellen, the county said the draft would probably come out in September. By Aug. 31, Permit Sonoma director Scott Orr told the Sonoma Index-Tribune that it would probably be spring 2027. "For the EIR we've got multiple different technical analyses that are proceeding at the same time and they all need to hit the finish line at the same time for the draft to be released," he said in the Index-Tribune's report. He named traffic impacts, land use and emergency access as linked sections that still had work left.
This is the county's second review of the campus. The Board of Supervisors adopted a Specific Plan for the site in December 2022. After a Sonoma County Superior Court ruling in October 2024, the board decertified that plan's environmental report and repealed the plan. The new review covers a revised Specific Plan and the Eldridge Renewal proposal together.
There is also a separate case against the state. In March 2026, Judge Pat Broderick allowed Sonoma Valley Next 100's lawsuit against the Department of General Services to go forward, according to the Sonoma Valley Sun. The remaining claims cover how the buyer was chosen, the timing of the development application, consultation on historic preservation, maintenance obligations and the land transfer to CAL FIRE. In September, the group was raising $150,000 to $200,000 for discovery, pretrial legal work and an alternative proposal of its own, the Press Democrat reported.
Some work on the review is happening on the campus now. In late September, temporary opaque construction fencing was moved around the property for subsurface work ahead of the environmental report. Permit Sonoma told the Sonoma Valley Sun that the fencing keeps people out of active work areas and is not meant to block general access, as described in the Sun's Sept. 30 report.
Residents have been specific about what they want the review to answer. At the Aug. 3 Glen Ellen Forum meeting, attendees asked about evacuation, traffic, water, wildlife, construction noise and the town's small-town character, the Press Democrat reported. In September, Next 100 organizer Bean Anderson told the Press Democrat that the same concerns keep coming back: traffic and evacuation on two-lane Arnold Drive, the wildlife corridor and Glen Ellen's small-town charm.
Sonoma Land Trust has taken a similar position on the land itself. It warns that too much redevelopment could permanently damage biodiversity and the Sonoma Valley Wildlife Corridor, and says it will keep pushing for a reasonable, environmentally sound project. Traffic and emergency access are also on Orr's list of sections still being finished.
The scale matters because Glen Ellen's market is small. MLS figures for the third quarter of 2026 show 10 single-family sales in Glen Ellen, up from six a year earlier. The median price was $1,817,500 and the median time on market was 87 days. With so few sales, one quarter's median can swing a long way. The useful number is the count. At that pace, Glen Ellen resells about 40 houses a year. Phase 1 at Eldridge would build 241 homes on its own, and the full plan would build almost 25 times that annual resale count.
Sonoma County as a whole is moving faster. The California Association of Realtors reported a September 2026 countywide median of $875,000 for existing single-family homes, up 10.1% from September 2025, with a median of 61 days on market compared with 76 a year earlier. C.A.R.'s September release and the Glen Ellen quarterly figures measure different periods, so they show two different speeds rather than one trend. Even so, Glen Ellen houses are taking longer to sell, and a buyer usually has time to work through how a particular address relates to the campus.
Location within Glen Ellen makes a large difference. A house that uses the Harney Road gate to reach the trails gets the permanent part of Eldridge now, with State Parks already running the land and the trails already connected. A house whose daily trips run along Arnold Drive past the campus is more exposed to the part that is still open, which is how much gets built and when. The applicant's filed schedule puts construction on the campus between 2027 and 2036.
The draft environmental report comes first, in spring 2027 by the county's latest estimate. Board decisions, a sale closing and the first demolition would come after it. The Next 100 case against the state is running at the same time. A buyer who closes in Glen Ellen this winter will probably own the house through several of these stages before the first Phase 1 home is occupied. Our earlier Glen Ellen post covered paperwork that stays with a parcel through a sale. The Eldridge timeline is similar: it applies to every Glen Ellen address, and its effect depends on where the house sits.
If you are weighing a Glen Ellen property, or a house elsewhere in Sonoma Valley, and want to know how a specific parcel relates to the Eldridge timeline, the team at Ginger Martin + Co. can walk the ground with you, from the Harney Road gate to the property line. Get in touch.